August 2026 Update

Sol Systems and its partner, Q-Cells, continue construction of the Blossom Solar Project. Sitewide remediation is complete. Civil crews continue installing sediment traps and permanent fencing, grading, and completing trench staking and layout. Electrical work includes trenching, road crossings, conduit rough-in, and installation of junction boxes, inverters, inverter rock rings, SCADA racks, messenger cable, and combiner boxes. Mechanical crews have completed inverter pile installation and continue installing piles in the PV field and advancing racking activities. Module installation is also underway. Construction will continue across all workstreams next month, while module deliveries remain ongoing and are expected to conclude by September. We remain committed to filling at least 70% of project positions with Ohio residents.