Sol Systems and its partner, Q-Cells, continue construction of the Blossom Solar Project. Sitewide remediation and boring are complete. Civil crews continue installing sediment traps and permanent fencing, grading, and completing trench staking and layout. Electrical work includes trenching, road crossings, and installation of junction boxes, inverters, inverter rock rings, SCADA racks, messenger cable, and combiner boxes. DC installation and transformer terminations are also underway. Mechanical crews continue installing piles in the PV field, advancing racking activities, and installing modules. At the substation, utility backfeed and transformer energization have been completed. Construction will continue across all workstreams next month, and all module deliveries are now complete. We remain committed to filling at least 70% of project positions with Ohio residents.