Sol Systems and its partner, Q-Cells, continue construction of the Blossom Solar Project. Sitewide remediation remains underway, including stabilizing roads and exposed soils, protecting soil stockpiles, seeding, and mowing to control noxious weeds. Civil crews continue installing sediment traps and permanent fencing, grading, and completing trench staking and layout. Electrical work includes trenching, road crossings, conduit rough-in, and installation of junction boxes, inverters, inverter rock rings, SCADA racks, messenger cable, and combiner boxes. Mechanical crews continue installing piles for the inverters and PV field and advancing racking activities. The substation has achieved mechanical completion, marking a major project milestone. Construction will continue across all workstreams next month, with remediation remaining a key priority. Module deliveries are ongoing and expected to conclude by September. We remain committed to filling at least 70% of project positions with Ohio residents.