Sol Systems and its partner, Q-Cells, are continuing construction of the Blossom Solar Project. Civil crews have finished the sediment traps and are working to complete permanent fencing, grading, and seeding. Electrical work, including trenching and road crossings, is nearly complete, and crews are also installing junction boxes, SCADA racks, combiner boxes, DC cable, and terminations. Mechanical crews have finished all piles and racking, and module installation is ongoing. Next month, work will continue across all workstreams, and commissioning will begin, with mechanical completion expected. We remain committed to filling at least 70% of project positions with Ohio residents.