Sol Systems and our partner Q-Cells continue construction activities on the Blossom Solar Project. Remediation work continues sitewide by stabilizing roads & bare soils, and protecting soil stockpiles. Civil construction continues with installing sediment traps, grading, road base install, permanent fence install, and low water crossings. Boring activities such as HDPE fusing, pot holing for utility locates, and directional drilling. Electrical activities such as trenching, and road crossings continue. Mechanical activities such as pile installation for the inverters and PV field continue. Over the next month, all construction activities will continue with a focus on remediation work as the site prepares for large equipment deliveries to continue in April such as the GSU. We maintain our commitment to staffing the project with at least 70% Ohio residents.