Sol Systems and our partner Q-Cells continue civil construction activities on the Blossom Solar Project. As of the beginning of December, site crews have started remediation work sitewide by stabilizing roads & bare soils, restricting off-road travel, protecting soil stockpiles, and upgrading site entrances/exits. Construction continues with installing the silt fence, building out the construction entrance, installing sediment traps, grading, mowing, and seeding the site and its surrounding area. Electrical activities such as trenching and road crossings have started. Over the next month, civil construction activities will continue with focus on remediation work as the site prepares for large equipment deliveries to continue in January. Surveying will also continue, allowing for pile installation for the inverters, and permanent fence installation to begin once grading activities are completed within each working zone. We maintain our commitment to staffing the project with at least 70% Ohio residents.