April 2026 Update

Sol Systems and its partner, Q-Cells, continue construction of the Blossom Solar Project. Sitewide remediation includes stabilizing roads and exposed soils and protecting soil stockpiles. Civil crews are installing sediment traps, grading, placing road base, erecting permanent fencing, and building low-water crossings. Boring work includes HDPE fusion, potholing to locate utilities, and directional drilling. Electrical crews continue trenching, road crossings, and conduit rough-in, while mechanical crews install piles for the inverters and PV field. The main power transformer, grounding transformer, and the control enclosure have been delivered and set at the substation. Over the next month, all construction activities will continue, with remediation remaining a primary focus. We also remain committed to filling at least 70% of project positions with Ohio residents.