Sol Systems and our partner Q-Cells continue civil construction activities on the Blossom Solar Project. As of September, site crews continue installing the silt fence, building out the construction entrance, installing sediment traps, grading, and mowing the site and its surrounding area. Subgrade preparation is in place for large electrical equipment that will be installed as the project progresses. Over the next month, these civil construction activities will continue as the site prepares for large equipment deliveries to commence in October and November. We maintain our commitment to staffing the project with at least 70% Ohio residents.
Thank you to everyone who continues to support this project.