October 2025 Update

Sol Systems and our partner Q-Cells continue civil construction activities on the Blossom Solar Project. As of October, site crews continue installing the silt fence, building out the construction entrance, installing sediment traps, grading, mowing,  and seeding the site and its surrounding area. Over the next month, these civil construction activities will continue as the site prepares for large equipment deliveries to commence in November. Surveying is being completed to allow for start of pile installation for inverters and installation of the permanent project fence this next month. We maintain our commitment to staffing the project with at least 70% Ohio residents.