Sol Systems and its partner, Q-Cells, continue construction of the Blossom Solar Project. Sitewide remediation remains underway, including road and exposed-soil stabilization, soil stockpile protection, seeding, and mowing to control noxious weeds. Civil crews are also installing sediment traps, grading, and erecting permanent fencing. Boring activities include HDPE fusion, potholing for utility locations, and directional drilling. Electrical work continues with trenching, road crossings, and conduit rough-in, alongside the installation of junction boxes, inverters, inverter rock rings, and SCADA racks. Mechanical crews continue installing piles for the inverters and PV field and have begun racking activities. Construction will proceed across all workstreams next month, with remediation remaining a key priority. We also remain committed to filling at least 70% of project positions with Ohio residents.