Sol Systems and our partner Q-Cells continue construction activities on the Blossom Solar Project. Remediation work continues sitewide by stabilizing roads & bare soils, restricting off-road travel, protecting soil stockpiles, and upgrading site entrances/exits. Civil construction continues with installing the silt fence, building out the construction entrance, installing sediment traps, grading, mowing, and seeding the site and its surrounding area. Electrical activities such as trenching and road crossings continue. Mechanical activities such as pile installation for the inverters and pile pinning along the array have started. Over the next month, all construction activities will continue with a focus on remediation work as the site prepares for large equipment deliveries to continue in February. Surveying will also continue, allowing for permanent fence installation to begin once grading activities are completed within each working zone. We maintain our commitment to staffing the project with at least 70% Ohio residents.